Page last updated at 22 Nov 2010

Vigilant LOP(R) achieves major milestone

A major milestone has been achieved in the Long Overhaul Period (Refuel) (LOP(R)) being undertaken by Babcock on HMS Vigilant at Devonport Royal Dockyard, with the successful completion of refuelling last week, two years in to the LOP(R) programme.

The refuelling of a nuclear submarine takes around seven months, from removing the reactor head to access the fuel modules to replacing the reactor head when refuelling is complete, and involves nearly 100 highly trained and experienced refuellers. The extremely complex and demanding procedure is carried out to the most rigorous of safety standards. Babcock has a considerable depth of knowledge and breadth of experience in this field, and is the only company in the country with the facilities and expertise to undertake open core reactor work on in-service submarines.

The refuel and subsequent reactor commissioning is a critical component of the three and a half year LOP(R) and dictates the overall programme duration. This is supported by a major revalidation of all reactor systems and replacement of major equipment such as the reactor pressure vessel head, main coolant pumps, and reactor instrumentation suite.

HMS Vigilant has now been refuelled with Core H, as used in the new Astute class submarines, providing power for the remainder of the submarine's operational life, without the need to refuel.

Commenting on this key milestone, Babcock submarine programme director, Gavin Leckie, said: "Refuelling a nuclear submarine is an exceptionally demanding project, and the refuel teams have been working tirelessly to achieve this successfully, to the highest possible safety standards. The end of the refuel signals the start of the final phase of the LOP(R) programme with the focus switching to commissioning submarine systems and reinstating the submarine structure in readiness for flood-up in the summer. The joint project team understands the strategic importance of achieving the key programme milestones in 2011 and is ready for the challenging year ahead."

The refuelling of HMS Vigilant was successfully completed on Friday 19 November.

 
Flood-up will take place in summer 2011 and the LOP(R) will complete in 2012, following sea trials of HMS Vigilant.

- ends -


NOTES TO EDITORS
In addition to the refuel and reactor work, the LOP(R) also sees a significant number of upgrades to the tactical and strategic weapons systems, as well as a vital and substantial overhaul of the propulsion system including main engines, 700KW motor generators, rehabilitation of the tailshaft and changing of the propulsor, plus major external represervation work, and upgrades to the accommodation and mess areas.

More than 2,000 personnel (including 500 skilled technicians and tradesmen) and 2.2 million manhours are involved in the LOP(R).

The refuelling operation can be split into six main phases. The first of these is preparation of the submarine to take the Refuelling Access House (RAH), involving removal of the submarine's rudder, a large section of the casing (weighing some eight tonnes) and cutting and removal of a section of the pressure hull. The 700 tonne RAH is then moved over the submarine, ready for the next phase which involves lifting the reactor compartment tunnel plug to gain access to the reactor. The teams then detension and remove the reactor pressure vessel (RPV) head nuts and studs, allowing access to the main seal membrane, which is cut to allow the RPV head to be removed. At this stage, the 'stack-up' is bolted on to the RPV core barrel to allow the water level to be raised, and all operations thereafter are carried out remotely within the water-filled stack-up. Fuel modules are removed, the core barrel cleaned and inspected, and new modules are installed. The final stage is to remove the stack up, replace the RPV head and weld the main seal membrane, followed by reinstallation onto the RPV head of new and refurbished components to operate and drive the control rods.

Related Links